30-Day Outlook

Construction is underway! Below is a list of upcoming construction activities. The 30-day outlook serves as a guide for upcoming construction. Construction schedules can change due to weather and other circumstances. This page is updated once a month.

North Segment

 

August 2017

The August Monthly Report will be the final update on the 35Express project as almost all The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org

Denton

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The pedestrian walkway and through lanes on the North Texas Boulevard bridge are scheduled for completion in August. The U-turn lanes on each end of the bridge are scheduled for completion in August.
     
  • The northbound I-35E entrance ramp from North Texas Boulevard, the southbound I-35E exit ramp to North Texas Boulevard are scheduled to open in August. The southbound I-35E entrance ramp from North Texas Boulevard and the northbound I-35E exit ramp to McCormick Street are scheduled to open in August.
     
  • The northbound I-35E exit ramp to North Texas Boulevard, the southbound I-35E entrance ramp from Fort Worth Drive and the northbound I-35E exit to Fort Worth Drive will shift to permanent configuration in August.
     
  • The southbound I-35E frontage road will be closed between McCormick Street and Lindsey Street for approximately two weeks in August.
     
  • The Post Oak Drive bridge is scheduled for completion in August with two through lanes in each direction as well as two turn lanes in each direction.

Corinth

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The Post Oak Drive bridge is scheduled for completion in August with two through lanes in each direction as well as two turn lanes in each direction.
     
  • The Oak Drive/Lake Dallas Drive intersection has opened. The northbound to southbound U-turn at the intersection will open in August.
     
  • The additional lanes of Turbeville Road/Hundley Drive are scheduled to open in August.
     
  • The additional north- and southbound I-35E mainlanes, frontage road lanes and pedestrian/bike paths on the Lewisville Lake bridges are scheduled to open this summer.
     
  • Work on Highland Village Road at the southbound I-35E frontage road is scheduled to be completed in August.
     
  • Work on Copperas Branch Park and Highland Lakes Park has begun and is scheduled for completion this summer.

Middle Segment

 

August 2017

Lewisville

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction 

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The additional lanes of the new Fox Avenue and Garden Ridge Boulevard bridges are scheduled to open in August.
     
  • The additional southbound mainlane has been opened between FM 407 and FM 3040/Round Grove Road. The additional north- and southbound I-35E mainlanes, frontage road lanes and pedestrian/bike paths on the Lewisville Lake bridges are scheduled to open in August.
     
  • Work on Highland Village Road at the southbound I-35E frontage road is scheduled to be completed in August.
     
  • Work on Copperas Branch Park and Highland Lakes Park has begun and are scheduled to be completed this summer.

Highland Village

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The Oak Drive/Lake Dallas Drive intersection has opened. The northbound to southbound U-turn at the intersection will open in August.
     
  • The additional north- and southbound I-35E mainlanes, frontage road lanes and pedestrian/bike paths on the Lewisville Lake bridges are scheduled to open this summer.
     
  • Work on Highland Village Road at the southbound I-35E frontage road is scheduled to be completed in August.
     
  • Work on Copperas Branch Park and Highland Lakes Park has begun and is scheduled for completion this summer.

Hickory Creek

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The Post Oak Drive bridge is scheduled for completion in August with two through lanes in each direction as well as two turn lanes in each direction.
     
  • The Oak Drive/Lake Dallas Drive intersection has opened. The northbound to southbound U-turn at the intersection will open in August.
     
  • The additional lanes of Turbeville Road/Hundley Drive are scheduled to open in August.
     
  • The additional north- and southbound I-35E mainlanes, frontage road lanes and pedestrian/bike paths on the Lewisville Lake bridges are scheduled to open this summer.
     
  • Work on Highland Village Road at the southbound I-35E frontage road is scheduled to be completed in August.
     
  • Work on Copperas Branch Park and Highland Lakes Park has begun and is scheduled for completion this summer.

Lake Dallas

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The Post Oak Drive bridge is scheduled for completion in August with two through lanes in each direction as well as two turn lanes in each direction.
     
  • The Oak Drive/Lake Dallas Drive intersection has opened. The northbound to southbound U-turn at the intersection will open in August.
     
  • The additional lanes of Turbeville Road/Hundley Drive are scheduled to open in August.
     
  • The additional north- and southbound I-35E mainlanes, frontage road lanes and pedestrian/bike paths on the Lewisville Lake bridges are scheduled to open this summer.
     
  • Work on Highland Village Road at the southbound I-35E frontage road is scheduled to be completed in August.
     
  • Work on Copperas Branch Park and Highland Lakes Park has begun and is scheduled for completion this summer.

South Segment

 

August 2017

Farmers Branch

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • Work on the ramps connecting the LBJ Express TEXpress Lanes to the 35Express TEXpress Lanes is scheduled for completion in August. Motorists should expect nightly closures of various north- and southbound mainlanes between Royal Lane and Interstate 635.
     
  • Work on the westbound I-635 to northbound I-35E mainlane bridge and the southbound I-35E bridge to eastbound I-635 mainlane bridge is scheduled for completion in August.

Carrollton

The August Monthly Report will be the final update on the 35Express project as almost all major operations are scheduled to be completed this month. For additional information, please contact the PI team by phone at 214-483-7777 or by email at info@35Express.org.

Construction

  • The final surface paving for the north- and southbound I-35E mainlanes will continue through late summer. There will be various nightly mainlane closures along the I-35E corridor for this work and motorists should be prepared for short term uneven pavement conditions and rough surfaces.
     
  • The additional lanes of the new elevated Belt Line Road intersection are scheduled to open in August. Overnight lane reductions and closures of the Belt Line Road intersection will continue until this work is completed.
     
  • The northbound exit to Belt Line Road and the southbound entrance ramp from Belt Line Road are scheduled to open in August.
     
  • Work on the south side of Dickerson Parkway east of I-35E is scheduled for completion in August. The new bridge and the northbound I-35E exit to Dickerson Parkway are scheduled to open in August.