30-Day Outlook

Construction is underway! Below is a list of upcoming construction activities. The 30-day outlook serves as a guide for upcoming construction. Construction schedules can change due to weather and other circumstances. This page is updated once a month.

North Segment

 

April 2017

Denton

Construction

  • The northbound I-35W ramp to northbound I-35E is scheduled to close nightly for approximately a week in April.
  • The northbound entrance ramp from North Texas Boulevard, the southbound exit ramp to North Texas Boulevard and the southbound entrance ramp from North Texas Boulevard are scheduled to open this spring.
  • The north- and southbound mainlanes at North Texas Boulevard are scheduled to shift into their permanent alignment by May.
  • Additional lanes of the North Texas Boulevard bridge are scheduled to open in April and work on the span is scheduled to be completed this spring.
  • McCormick Street is closed between the north- and southbound frontage roads through April for bridge construction. Traffic is free-flow on the frontage roads during this closure.
  • Work lengthening and widening the entrance and exit ramps between Fort Worth Drive and Teasley Lane continues. Traffic will use temporary ramps – such as the one in place at the southbound entrance ramp from Teasley Road – until the permanent ramps are completed. This work will continue into the spring.
  • The Post Oak Drive bridge is scheduled for completion this summer with two through lanes in each direction as well as two turn lanes in each direction. Work rebuilding the intersections on either side of the bridge has begun.
  • The northbound I-35E mainlanes between the U-turn at Destiny Dallas RV Park and Post Oak Drive are scheduled to shift east onto permanent pavement in April. All entrance and exit ramps will shift into their permanent alignment, and the northbound exit ramp to Post Oak Drive will reopen.

Corinth

Construction

  • The Post Oak Drive bridge is scheduled for completion this spring with two through lanes in each direction as well as two turn lanes in each direction. Work rebuilding the intersections on either side of the bridge has begun.
  • The northbound I-35E mainlanes between the U-turn at Destiny Dallas RV Park and Post Oak Drive are scheduled to shift east onto permanent pavement in April. All entrance and exit ramps will shift into their permanent alignment, and the northbound exit ramp to Post Oak Drive will reopen.
  • The north and southbound mainlanes between Garden Ridge Boulevard and Swisher road are now in their permanent configuration over the original Lewisville Lake bridge. The additional northbound mainlane, frontage road lanes and pedestrian/bike path are scheduled to open this summer.
  • Work on the new fencing along the pedestrian/bike path on the west side of the new Lewisville Lake bridge has begun. The path and the southbound frontage road lanes are scheduled for completion this summer.

Middle Segment

 

April 2017

Lewisville

Construction 

  • The north- and southbound collector/distributor lanes between the Sam Rayburn Tollway and the President George Bush Turnpike are open.
  • The FM 407 intersection is expected to fully reopen this spring. Crews are finalizing the decorative paving and aesthetic work on the interchange.  
  • Work continues on the new Fox Avenue and Garden Ridge Boulevard bridges with additional lanes on both spans scheduled to be opened this spring. 
  • The northbound mainlanes between Garden Ridge Boulevard and Swisher road are now in their permanent configuration over the original Lewisville Lake bridge. The additional northbound mainlane, frontage road lanes and pedestrian/bike path are scheduled to open this spring.

Highland Village

Construction

  • Work on Highland Village Road at the I-35E southbound frontage road is scheduled for completion this spring.
  • Construction of Copperas Branch Park and Highland Lakes Park are scheduled to begin this spring.
  • Work on the new fencing along the pedestrian/bike path on the west side of the new Lewisville Lake bridge has begun. The path and the southbound frontage road lanes are scheduled for completion this summer.
  • The north and southbound mainlanes between Garden Ridge Boulevard and Swisher road are now in their permanent configuration over the original Lewisville Lake bridge. The additional northbound mainlane, frontage road lanes and pedestrian/bike path are scheduled to open this summer.
  • The northbound I-35E mainlanes between the U-turn at Destiny Dallas RV Park and Post Oak Drive are scheduled to shift east onto permanent pavement in April. The northbound exit ramp to Post Oak Drive will reopen.
     

Hickory Creek

Construction

  • The northbound I-35E mainlanes between the U-turn at Destiny Dallas RV Park and Post Oak Drive are scheduled to shift east onto permanent pavement late April. The northbound exit ramp to Post Oak Drive will reopen.
  • Work continues on the new Turbeville Road/Hundley Drive underpass and the new Oak/Lake Dallas Drive underpass. The additional lanes for each intersection are scheduled to open this summer.
  • The north and southbound mainlanes between Garden Ridge Boulevard and Swisher road are now in their permanent configuration over the original Lewisville Lake bridge. The additional northbound mainlane, frontage road lanes and pedestrian/bike path are scheduled to open this summer.
  • Work on the new fencing along the pedestrian/bike path on the west side of the new Lewisville Lake bridge has begun. The path and the southbound frontage road lanes are scheduled for completion this summer.
     

Lake Dallas

Construction

  • The northbound I-35E mainlanes between the U-turn at Destiny Dallas RV Park and Post Oak Drive are scheduled to shift east onto permanent pavement late April. The northbound exit ramp to Post Oak Drive will reopen.
  • Work continues on the new Turbeville Road/Hundley Drive underpass and the new Oak/Lake Dallas Drive underpass. Both are scheduled for completion this summer.
  • The north and southbound mainlanes between Garden Ridge Boulevard and Swisher road are now in their permanent configuration over the original Lewisville Lake bridge. The additional northbound mainlane, frontage road lanes and pedestrian/bike path are scheduled to open this summer.
  • Work on the new fencing along the pedestrian/bike path on the west side of the new Lewisville Lake bridge has begun. The path and the southbound frontage road lanes are scheduled for completion this summer.
     

South Segment

 

April 2017

Farmers Branch

Construction

  • Bridge construction for the ramps that will connect the I-635 and I-35E TEXpress lanes continues. Motorists should expect nightly closures of various north- and southbound mainlanes between Royal Lane and Interstate 635 in April.
  • Work on the westbound I-635 to northbound I-35E bridge and the southbound I-35E bridge to eastbound I-635 will continue through April.
  • Rehabilitation work on the Valwood Parkway bridge is scheduled for completion in April. The U-turn lanes will be re-opened when this is complete.
  • The north- and southbound collector/distributor lanes between the Sam Rayburn Tollway and the President George Bush Turnpike are open. 

Carrollton

Construction

  • Work continues at the new elevated Belt Line Road interchange. While this work is underway, motorists should expect overnight lane reductions and closures of the Belt Line Road intersection.
  • East- and westbound Belt Line Road traffic have shifted onto the new elevated intersection. Additional lanes of the Belt Line Road intersection are scheduled to open this summer.
  • Work on Broadway Street south of Belt Line Road will continue into summer. Old Downtown Carrollton traffic will use Main Street during this closure. 
  • The north- and southbound collector/distributor lanes between the Sam Rayburn Tollway and the President George Bush Turnpike are open.